Achlachan Wind Farm (10 MW)

Achlachan Wind Farm is a 10 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 April 2019; the record was last updated on 24 June 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
24 June 2019record last updated
Highlandcouncil area

Planning timeline

DateStage
11 April 2013Application submitted
13 November 2013Planning permission granted
15 October 2016Construction started
8 April 2019Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
24 June 2019
Operator or applicant
Whirlwind Renewables
Planning authority
Highland
Planning application reference
13/01190/FUL
Turbines
5
Turbine height
115 m
Address (REPD)
Achlachan Windfarm Watten
Council area (by location)
Highland
Time to decision
31 weeks
Contracts for Difference
AR1
REPD reference
4330

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mybster Farm, Wattenbattery storage19.8application withdrawn0.7
Achlachan Wind Farm - Phase 2wind farm6.9abandoned0.9
Halsary Wind Farmwind farm34operational2.1
Spittal Mains Quarrybattery storage49.9approved, not built2.4
Spittal Mains, Spittalbattery storage300application submitted2.4
Wind Farm at Achlachan Windfarmwind farm8.5approved, not built2.8
Achiesbattery storage162application submitted2.8
Bad a Cheo Wind Farmwind farm26.7operational3.5
Tormsdale -Wind Farmwind farm50application submitted4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4489, -3.4546).