Achairn (6.2 MW wind farm)

Achairn is a 6.2 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 May 2009; the record was last updated on 9 June 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWwind farm
operationalstatus in REPD
9 June 2010record last updated
Highlandcouncil area

Planning timeline

DateStage
11 August 2004Application submitted
1 March 2006Planning permission granted
1 April 2009Construction started
20 May 2009Operational

Project details

Technology
wind farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
9 June 2010
Operator or applicant
Messrs James and Ronald Innes
Planning authority
Highland
Planning application reference
CA2004366
Turbines
3
Address (REPD)
West of Wick, Caithness
Council area (by location)
Highland
Time to decision
81 weeks
REPD reference
3285

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wathegar 2 Wind Farmwind farm18.5operational0.9
Wathegar wind farmwind farm10operational1.4
Camster IIwind farm36operational2.6
Camsterwind farm50operational5.3
Cogle Moss Wind Farmwind farm36permission expired5.9
Causeymirewind farm48.3operational6.8
Watten Wind Farmwind farm47.6application withdrawn6.9
Cnoc Morailwind farm11.5refused8.0
Burn of Whilkwind farm22.5operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4385, -3.2015).