Energy Projects Near You

Solar, wind and battery projects near Charlestown of Aberlour (AB38)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB38 (Moray): 4 are waiting for a planning decision, 4 approved but not yet running, 2 operational. The largest live scheme is Rothes Wind Farm III (132 MW wind farm, approved on 22 October 2022, not yet built), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
4awaiting a decision
4approved, not running
2operational

Projects within 10 km of AB38

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Craigellachie Biomass CHP Plant, Craigellachie- Solar Farmsolar farmsolar farm4approved, not builtupdated Jan 2024Sep 2023granted Jan 2024Jan 2024Moray2.9
Teindland Wind Farmwind farmwind farm85application submittedupdated Aug 2025Jul 2025—Aug 2025Moray4.7
Rothes Wind Farm IIIwind farmwind farm132approved, not builtupdated Oct 2022Feb 2019granted Oct 2022Oct 2022Moray6.5
Craig Watch Wind Farm & Battery Storagewind farmwind farm72.6application submitted may be out of dateupdated Jul 2022Jun 2022—Jul 2022Moray7.3
Garbet Windfarm Wind Farm & Storage facilitywind farmwind farm46.2under constructionupdated Jul 2025Jan 2021granted Nov 2021Jul 2025Moray7.3
Craig Watch Wind Farm & Battery Storagebattery storagebattery storage27.4application submitted may be out of dateupdated Jul 2022Jun 2022—Jul 2022Moray7.3
Garbet Windfarm Wind Farm & Storage facilitybattery storagebattery storage3under constructionupdated Jul 2025Jan 2021granted Nov 2021Jul 2025Moray7.3
Rothes Wind (Cairn Uish)wind farmwind farm50.6operationalupdated May 2017Sep 2001granted Jan 2003May 2017Moray10.0
Rothes Wind Farm (Extension) (II)wind farmwind farm41.4operationalupdated Aug 2013Dec 2007granted Jan 2010Aug 2013Moray10.0
Cairn Uish Wind Farm Extensionwind farmwind farm21application withdrawnupdated Aug 2004——Aug 2004Moray10.0
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Teindland Wind Farmwind farmwind farm—application submittedupdated Aug 2025Jul 2025—Aug 2025Moray4.7

Distance from the average position of the AB38 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101004
Wind farm83220336
Battery storage2110030.4

MW in pipeline: pending, approved and under-construction capacity.

How Moray decides solar, wind and battery applications

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

All projects in Moray

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB38, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.