Loanhead Farm (49.9 MW battery storage)

Loanhead Farm is a 49.9 MW battery storage project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 26 May 2025, no decision recorded; the record was last updated on 27 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application submittedstatus in REPD
27 June 2025record last updated
Moraycouncil area

Planning timeline

DateStage
26 May 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
27 June 2025
Operator or applicant
OPDE UK Limted
Planning authority
Moray
Planning application reference
25/00469/APP
Address (REPD)
Loanhead Farm, Elgin
Council area (by location)
Moray
Name in REPD
Loanhead Farm - Battery Energy Storage System
REPD reference
16619

Who decides

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bishopmillbattery storage30approved, not built3.9
Hill of Towie (Drummuir)wind farm48operational5.1
Hill of Towie II Wind Farmwind farm48permission expired5.1
RAF Lossiemouthsolar farm5application submitted6.4
Milltown Airfield (Speyslaw)solar farm50approved, not built8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6653, -3.3756).