Energy Projects Near You

Hill of Glaschyle Wind Farm (27.6 MW)

Hill of Glaschyle Wind Farm is a 27.6 MW wind farm project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2016; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.6 MWwind farm
operationalstatus in REPD
4 April 2017record last updated
Moraycouncil area

Planning timeline

DateStage
14 January 2013Application submitted
18 December 2013Refused by the planning authority
31 March 2014Planning permission granted
31 March 2014Appeal allowed
1 June 2016Construction started
1 December 2016Operational

Project details

Technology
wind farm
Capacity
27.6 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
Muirden Energy
Planning authority
Moray
Planning application reference
13/00053/EIA
Appeal reference
14/00001/REF
Turbines
12
Turbine height
99 m
Address (REPD)
Hill Of Glaschyle Logie Forres Moray
Council area (by location)
Moray
Time to decision
63 weeks
REPD reference
4381

Who decides

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clash Gourwind farm225approved, not built5.6
Cairn Duhie Wind Farmwind farm67.2approved, not built7.4
Ourackwind farm105approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5105, -3.6156).