Cairn Duhie Wind Farm (67.2 MW)

Cairn Duhie Wind Farm is a 67.2 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 February 2024, not yet built; the record was last updated on 23 February 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

67.2 MWwind farm
approved, not builtstatus in REPD
23 February 2026record last updated
Highlandcouncil area

Planning timeline

DateStage
26 March 2021Application submitted
2 February 2024Section 36 consent granted (Scottish Ministers)
2 February 2029Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
67.2 MW
Status (REPD)
approved, not built
Record last updated
23 February 2026
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003225
Turbines
16
Turbine height
150 m
Address (REPD)
Cairn Duhie Wind Farm Ferness Nairnshire
Council area (by location)
Highland
Time to decision
149 weeks
Contracts for Difference
AR7a
REPD reference
7710

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Cairn Duhie EC00002087605 November 2013replaced by a revised application
Cairn Duhie Wind Farm ECU0000322567.226 March 2021approved on 2 February 2024, not yet built

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill of Glaschyle Wind Farmwind farm27.6operational7.4
Ourackwind farm105approved, not built8.2
Lethen Wind Farm Wind Turbines and Energy Storagewind farm102refused8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4644, -3.7059).