Lethen Wind Farm Wind Turbines and Energy Storage (102 MW)

Lethen Wind Farm Wind Turbines and Energy Storage is a 102 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 23 February 2024; the record was last updated on 10 April 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

102 MWwind farm
refusedstatus in REPD
10 April 2024record last updated
Highlandcouncil area

Planning timeline

DateStage
21 January 2022Application submitted
23 February 2024Refused by the planning authority

Project details

Technology
wind farm
Capacity
102 MW
Status (REPD)
refused
Record last updated
10 April 2024
Operator or applicant
Fred Olsen Renewables Ltd
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002216
Turbines
17
Turbine height
185 m
Address (REPD)
Land 4700M NW Of Gamekeepers Cottage Nairn
Council area (by location)
Highland
Time to decision
109 weeks
Name in REPD
Lethen Wind Farm Wind Turbines and Energy Storage
REPD reference
8489

The scheme also includes 10 MW of battery storage, recorded separately in REPD (refused).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tom Na Clach Wind Farm Extensionwind farm31.5approved, not built6.7
Tom Nan Clachwind farm39operational6.8
Glenkirkwind farm93refused7.9
Cairn Duhie Wind Farmwind farm67.2approved, not built8.4
Balnespick Wind Farmwind farm55.8application submitted8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3995, -3.7792).