Balnespick Wind Farm (55.8 MW)

Balnespick Wind Farm is a 55.8 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 20 February 2025, no decision recorded; the record was last updated on 7 March 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

55.8 MWwind farm
application submittedstatus in REPD
7 March 2025record last updated
Scotlandcouncil area

Planning timeline

DateStage
20 February 2025Application submitted

Project details

Technology
wind farm
Capacity
55.8 MW
Status (REPD)
application submitted
Record last updated
7 March 2025
Operator or applicant
Fred Olsen Renewables Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004904
Turbines
9
Turbine height
200 m
Address (REPD)
5 km east of Tomatin, 6 km north-west of Carrbridge
Council area (by location)
not known
REPD reference
14768

The scheme also includes 10 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Glenkirkwind farm93refused1.7
Tom Na Clach Wind Farm Extensionwind farm31.5approved, not built4.4
Tom Nan Clachwind farm39operational5.4
Lynemore Wind Farmbattery storage50application submitted7.1
Lynemore Wind Farmwind farm101application submitted7.1
Wind Farm at 27km SE of Inverness 13km NW of Aviemorewind farm187application submitted7.1
Clune Wind Farmbattery storage100application submitted7.1
Tomatinwind farm25.5refused8.2
Lethen Wind Farm Wind Turbines and Energy Storagewind farm102refused8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3449, -3.8852).