Energy Projects Near You

Tomatin (25.5 MW wind farm)

Tomatin is a 25.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 August 2013; the record was last updated on 31 March 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25.5 MWwind farm
refusedstatus in REPD
31 March 2011record last updated
Highlandcouncil area

Planning timeline

DateStage
24 June 2009Application submitted
29 August 2013Refused by the planning authority

Project details

Technology
wind farm
Capacity
25.5 MW
Status (REPD)
refused
Record last updated
31 March 2011
Operator or applicant
Nanclach Ltd
Planning authority
Highland
Planning application reference
09/00439/FUL
Turbines
17
Address (REPD)
Inverness, Highlands, IV33
Council area (by location)
Highland
Time to decision
218 weeks
REPD reference
2698

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wind Farm at 27km SE of Inverness 13km NW of Aviemorewind farm187application submitted1.1
Clune Wind Farmbattery storage100application submitted1.1
Lynemore Wind Farmwind farm101application submitted1.1
Lynemore Wind Farmbattery storage50application submitted1.1
Glen Kyllachy Wind Farmwind farm48.5operational4.5
Farr Wind Farmwind farm92operational5.0
Moy Wind Farmwind farm40abandoned5.4
Moy Wind Farm (2nd Application)wind farm66operational5.4
Glenkirkwind farm93refused8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3426, -4.0217).