Tomatin (25.5 MW wind farm)
Tomatin is a 25.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 August 2013; the record was last updated on 31 March 2011.
25.5 MWwind farm
refusedstatus in REPD
31 March 2011record last updated
Highlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 June 2009 | Application submitted |
| 29 August 2013 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 25.5 MW
- Status (REPD)
- refused
- Record last updated
- 31 March 2011
- Operator or applicant
- Nanclach Ltd
- Planning authority
- Highland
- Planning application reference
- 09/00439/FUL
- Turbines
- 17
- Address (REPD)
- Inverness, Highlands, IV33
- Council area (by location)
- Highland
- Time to decision
- 218 weeks
- REPD reference
- 2698
Who decides
| Applications | Highland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 160 | 10,236 |
| Refused | 68 (42%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Onshore wind refused | 61 of 114 | 45% |
| Battery storage refused | 7 of 31 | 16% |
| Median time from submission to decision | 52.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 20 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Wind Farm at 27km SE of Inverness 13km NW of Aviemore | wind farm | 187 | application submitted | 1.1 |
| Clune Wind Farm | battery storage | 100 | application submitted | 1.1 |
| Lynemore Wind Farm | wind farm | 101 | application submitted | 1.1 |
| Lynemore Wind Farm | battery storage | 50 | application submitted | 1.1 |
| Glen Kyllachy Wind Farm | wind farm | 48.5 | operational | 4.5 |
| Farr Wind Farm | wind farm | 92 | operational | 5.0 |
| Moy Wind Farm | wind farm | 40 | abandoned | 5.4 |
| Moy Wind Farm (2nd Application) | wind farm | 66 | operational | 5.4 |
| Glenkirk | wind farm | 93 | refused | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3426, -4.0217).