Moy Wind Farm (40 MW)

Moy Wind Farm is a 40 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 27 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWwind farm
abandonedstatus in REPD
27 January 2014record last updated
Highlandcouncil area

Planning timeline

DateStage
5 April 2011Application submitted
29 February 2012Refused by the planning authority
29 February 2012Planning permission granted
29 February 2012Appeal allowed

Project details

Technology
wind farm
Capacity
40 MW
Status (REPD)
abandoned
Record last updated
27 January 2014
Operator or applicant
Carbon Free Developments Ltd
Planning authority
Highland
Planning application reference
11/01205/FUL
Appeal reference
PPA-270-2063
Turbines
20
Address (REPD)
Tomatin, Invernessshire
Council area (by location)
Highland
Time to decision
47 weeks
REPD reference
3719

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Moy Wind Farm (2nd Application)wind farm66operational<0.1
Daviot Wind Farmwind farm32.5refused on appeal4.0
Tomatinwind farm25.5refused5.4
Lynemore Wind Farmwind farm101application submitted5.8
Lynemore Wind Farmbattery storage50application submitted5.8
Wind Farm at 27km SE of Inverness 13km NW of Aviemorewind farm187application submitted5.9
Clune Wind Farmbattery storage100application submitted5.9
Farr Wind Farmwind farm92operational6.9
Glen Kyllachy Wind Farmwind farm48.5operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3888, -4.0488).