Daviot Wind Farm (32.5 MW)
Daviot Wind Farm is a 32.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 11 February 2013; the record was last updated on 19 April 2013.
32.5 MWwind farm
refused on appealstatus in REPD
19 April 2013record last updated
Highlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 5 January 2012 | Application submitted |
| 25 June 2012 | Refused by the planning authority |
| 11 February 2013 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 32.5 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 19 April 2013
- Operator or applicant
- West Coast Energy
- Planning authority
- Highland
- Planning application reference
- 12/00036/FUL
- Appeal reference
- 12/00032/REFIN
- Turbines
- 13
- Address (REPD)
- Lairgandour Daviot Inverness IV2 6XN
- Council area (by location)
- Highland
- Time to decision
- 25 weeks
- REPD reference
- 3882
Who decides
| Applications | Highland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 160 | 10,236 |
| Refused | 68 (42%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Onshore wind refused | 61 of 114 | 45% |
| Battery storage refused | 7 of 31 | 16% |
| Median time from submission to decision | 52.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 20 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Moy Wind Farm (2nd Application) | wind farm | 66 | operational | 4.0 |
| Moy Wind Farm | wind farm | 40 | abandoned | 4.0 |
| Carr Ban Wind Farm | wind farm | 23.8 | application withdrawn | 6.8 |
| Wind Turbines at Kyllachy Wind Farm | wind farm | 78 | application submitted | 7.8 |
| Kyllachy Wind Farm | battery storage | 22 | application submitted | 7.8 |
| Farr Wind Farm | wind farm | 92 | operational | 8.0 |
| Corriegarth 2 | wind farm | 67.2 | approved, not built | 8.0 |
| Fairways Business Park | battery storage | 50 | refused | 8.2 |
| Tomatin | wind farm | 25.5 | refused | 8.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4057, -4.1071).