Energy Projects Near You

Lynemore Wind Farm (50 MW)

Lynemore Wind Farm is a 50 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 1 May 2025, no decision recorded; the record was last updated on 8 July 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
application submittedstatus in REPD
8 July 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
1 May 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
application submitted
Record last updated
8 July 2025
Operator or applicant
Galileo Empower UK Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005105
Address (REPD)
2000M SW Of Lynemore Moy
Council area (by location)
Highland
Name in REPD
Lynemore Wind Farm
REPD reference
16397

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Lynemore Wind Farmwind farm101application submitted<0.1
Wind Farm at 27km SE of Inverness 13km NW of Aviemorewind farm187application submitted<0.1
Clune Wind Farmbattery storage100application submitted<0.1
Tomatinwind farm25.5refused1.1
Glen Kyllachy Wind Farmwind farm48.5operational5.5
Moy Wind Farm (2nd Application)wind farm66operational5.8
Moy Wind Farmwind farm40abandoned5.8
Farr Wind Farmwind farm92operational6.1
Balnespick Wind Farmwind farm55.8application submitted7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3427, -4.0027).