Energy Projects Near You

Tom Nan Clach (39 MW wind farm)

Tom Nan Clach is a 39 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2019; the record was last updated on 17 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39 MWwind farm
operationalstatus in REPD
17 September 2020record last updated
Highlandcouncil area

Planning timeline

DateStage
27 August 2015Application submitted
26 January 2016Refused by the planning authority
15 March 2016Appeal lodged
15 June 2016Construction started
28 October 2016Appeal allowed
24 April 2018Planning permission granted
1 March 2019Operational

Project details

Technology
wind farm
Capacity
39 MW
Status (REPD)
operational
Record last updated
17 September 2020
Operator or applicant
Infinergy
Planning authority
Highland
Planning application reference
15/03286/FUL
Appeal reference
PPA-270-2150
Turbines
13
Turbine height
125 m
Address (REPD)
Approximately 8km North East Of Tomatin, Drynachan Nairnshire
Council area (by location)
Highland
Time to decision
139 weeks
Contracts for Difference
AR1
REPD reference
4420

Earlier applications for this site

ApplicationMWSubmittedOutcome
Tom Nan Clach Wind Farm 09/00439/FULIN39.11 June 2009refused 23 August 2010

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tom Na Clach Wind Farm Extensionwind farm31.5approved, not built1.0
Glenkirkwind farm93refused3.6
Balnespick Wind Farmwind farm55.8application submitted5.4
Lethen Wind Farm Wind Turbines and Energy Storagewind farm102refused6.8
Lynemore Wind Farmbattery storage50application submitted8.7
Lynemore Wind Farmwind farm101application submitted8.7
Clune Wind Farmbattery storage100application submitted8.7
Wind Farm at 27km SE of Inverness 13km NW of Aviemorewind farm187application submitted8.7
Moy Wind Farmwind farm40abandoned9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3929, -3.8917).