Tom Na Clach Wind Farm Extension (31.5 MW)

Tom Na Clach Wind Farm Extension is a 31.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 May 2024, not yet built; the record was last updated on 10 July 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31.5 MWwind farm
approved, not builtstatus in REPD
10 July 2024record last updated
Highlandcouncil area

Planning timeline

DateStage
6 April 2022Application submitted
10 May 2024Section 36 consent granted (Scottish Ministers)
10 May 2029Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
31.5 MW
Status (REPD)
approved, not built
Record last updated
10 July 2024
Operator or applicant
Infinergy Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003453
Turbines
7
Turbine height
150 m
Address (REPD)
Tom Nan Clach Wind Farm, Glenferness
Council area (by location)
Highland
Time to decision
109 weeks
Name in REPD
Tom Na Clach - Wind Farm Extension
REPD reference
10998

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tom Nan Clachwind farm39operational1.0
Glenkirkwind farm93refused2.7
Balnespick Wind Farmwind farm55.8application submitted4.4
Lethen Wind Farm Wind Turbines and Energy Storagewind farm102refused6.7
Lynemore Wind Farmwind farm101application submitted8.3
Lynemore Wind Farmbattery storage50application submitted8.3
Wind Farm at 27km SE of Inverness 13km NW of Aviemorewind farm187application submitted8.3
Clune Wind Farmbattery storage100application submitted8.3
Tomatinwind farm25.5refused9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3846, -3.8879).