Clash Gour (225 MW wind farm)

Clash Gour is a 225 MW wind farm project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 April 2022, not yet built; the record was last updated on 24 October 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

225 MWwind farm
approved, not builtstatus in REPD
24 October 2023record last updated
Scotlandcouncil area

Planning timeline

DateStage
17 December 2018Application submitted
19 April 2022Section 36 consent granted (Scottish Ministers)
21 October 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
225 MW
Status (REPD)
approved, not built
Record last updated
24 October 2023
Operator or applicant
EDF Energy Renewables/ Force 9
Planning authority
Scottish Government (S36)
Planning application reference
ECU00000738
Turbines
48
Turbine height
176 m
Address (REPD)
located to the southwest, north and east of Berry Burn
Council area (by location)
not known
Time to decision
174 weeks
Contracts for Difference
AR5
REPD reference
6372

The scheme also includes 50 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Berry Burnwind farm66.7operational5.6
Berry Burn Wind Farm (extension)wind farm37.8approved, not built5.6
Hill of Glaschyle Wind Farmwind farm27.6operational5.6
Pauls Hill 2wind farm28approved, not built5.6
Paul's Hill and Extensionwind farm65operational5.6
Ourackwind farm105approved, not built6.7
Meikle Hill wind farmwind farm13.8permission expired9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.485, -3.5353).