Meikle Hill wind farm (13.8 MW)

Meikle Hill wind farm is a 13.8 MW wind farm project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 24 June 2018; the record was last updated on 29 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
permission expiredstatus in REPD
29 October 2018record last updated
Moraycouncil area

Planning timeline

DateStage
16 June 2014Application submitted
24 June 2015Planning permission granted
24 June 2018Permission expired

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
permission expired
Record last updated
29 October 2018
Operator or applicant
Brookfield Renewable Energy Group (PNE Wind UK)
Planning authority
Moray
Planning application reference
14/01087/EIA
Turbines
6
Address (REPD)
Meikle Hill Dallas Moray
Council area (by location)
Moray
Time to decision
53 weeks
REPD reference
4305

Who decides

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cairn Uish Wind Farm Extensionwind farm21application withdrawn3.4
Rothes Wind Farm (Extension) (II)wind farm41.4operational3.4
Rothes Wind (Cairn Uish)wind farm50.6operational3.4
Kellas Wind Farmbattery storage30approved, not built3.5
Kellas Wind Farmwind farm38.4approved, not built3.5
Kellas Wind Farmwind farm18.4permission expired3.6
Rothes Wind Farm IIIwind farm132approved, not built6.5
Clash Gourwind farm225approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5381, -3.4197).