Paul's Hill and Extension (65 MW wind farm)

Paul's Hill and Extension is a 65 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2006; the record was last updated on 4 October 2017. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

65 MWwind farm
operationalstatus in REPD
4 October 2017record last updated
Highlandcouncil area

Planning timeline

DateStage
30 September 2001Application submitted
31 March 2003Section 36 consent granted (Scottish Ministers)
1 January 2004Construction started
1 April 2006Operational

Project details

Technology
wind farm
Capacity
65 MW
Status (REPD)
operational
Record last updated
4 October 2017
Operator or applicant
Fred Olsen Renewables
Planning authority
Scottish Government (S36)
Planning application reference
IEC3/99
Turbines
28
Address (REPD)
Paul's Hill, Bowlingalloch, Moray, (area is also known as Ballindalloch) (14km west of Charlestown, 13km north of Granthon on Spey)
Council area (by location)
Highland
Time to decision
78 weeks
REPD reference
4687

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Pauls Hill 2wind farm28approved, not built<0.1
Berry Burnwind farm66.7operational0.1
Berry Burn Wind Farm (extension)wind farm37.8approved, not built0.1
Clash Gourwind farm225approved, not built5.6
Ourackwind farm105approved, not built6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4462, -3.4762).