Energy Projects Near You

Aultmore Forest - Buckie - Windfarm (50 MW)

Aultmore Forest - Buckie - Windfarm is a 50 MW battery storage project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 28 February 2024, no decision recorded; the record was last updated on 8 March 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
application submittedmay be out of datestatus in REPD
8 March 2024record last updated
Moraycouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
28 February 2024Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
application submitted
Record last updated
8 March 2024
Operator or applicant
Vattenfall
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003365
Address (REPD)
Aultmore Forest, Drybridge, Buckie
Council area (by location)
Moray
REPD reference
15995

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Aultmore Forest - Buckie - Windfarmwind farm106application submitted<0.1
Blackhillock Electricity Substationbattery storage300under construction0.8
Electricity Substation, Westerton Roadbattery storage49.9approved, not built1.8
Gibson Farm, Blackhillockbattery storage349approved, not built2.1
Drum Farmbattery storage49.9approved, not built2.2
Edintore Wind Farmwind farm18operational2.4
Bodinfinnoch Wind Farmwind farm13.8refused on appeal3.9
Cairnborrowwind farm10operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5249, -2.9436).