Energy Projects Near You

Edintore Wind Farm (18 MW)

Edintore Wind Farm is an 18 MW wind farm project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 October 2016; the record was last updated on 31 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
operationalstatus in REPD
31 October 2016record last updated
Moraycouncil area

Planning timeline

DateStage
11 December 2010Application submitted
14 December 2011Refused by the planning authority
28 August 2012Planning permission granted
28 August 2012Appeal allowed
24 September 2015Construction started
31 October 2016Operational

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
31 October 2016
Operator or applicant
Vento Ludens
Planning authority
Moray
Planning application reference
10/02092/EIA
Appeal reference
12/00010/REF
Turbines
6
Address (REPD)
Edintore, Keith, Moray
Council area (by location)
Moray
Time to decision
89 weeks
REPD reference
4072

Who decides

ApplicationsMorayUK
Decided applications (solar, wind, battery)2110,236
Refused7 (33%)19%
Solar refused0 of 212%
Onshore wind refused7 of 1445%
Battery storage refused0 of 516%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed4 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blackhillock Electricity Substationbattery storage300under construction1.7
Aultmore Forest - Buckie - Windfarmwind farm106application submitted2.4
Aultmore Forest - Buckie - Windfarmbattery storage50application submitted2.4
Bodinfinnoch Wind Farmwind farm13.8refused on appeal3.9
Gibson Farm, Blackhillockbattery storage349approved, not built4.2
Electricity Substation, Westerton Roadbattery storage49.9approved, not built4.2
Drum Farmbattery storage49.9approved, not built4.6
Cairnborrowwind farm10operational6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5057, -2.9625).