Dorenell Wind Farm (extension) (175 MW)

Dorenell Wind Farm (extension) is a 175 MW wind farm project in Moray, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 27 April 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

175 MWwind farm
abandonedstatus in REPD
27 April 2018record last updated
Moraycouncil area

Planning timeline

DateStage
12 December 2014Application submitted
2 June 2016Refused by the planning authority
22 September 2016Appeal lodged

Project details

Technology
wind farm
Capacity
175 MW
Status (REPD)
abandoned
Record last updated
27 April 2018
Operator or applicant
EDF Energy Renewables
Planning authority
Scottish Government (S36)
Planning application reference
EC00003111
Appeal reference
WIN-300-2
Turbines
53
Turbine height
150 m
Address (REPD)
Glenlivet Estate, Dufftown, Speyside, Moray
Council area (by location)
Moray
Time to decision
77 weeks
REPD reference
5051

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dorenell Wind Farm (Previously Site A and B Scaut Hill)wind farm177operational<0.1
Dorenell Extension Wind Farmwind farm477application submitted7.9
Clashindarroch Wind Farm Extensionwind farm139approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.3509, -3.1317).