Brownieleys - 3 Wind Turbines (7.5 MW)

Brownieleys - 3 Wind Turbines is a 7.5 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 February 2017; the record was last updated on 28 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
28 February 2017record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
13 April 2012Application submitted
1 April 2013Refused by the planning authority
1 October 2013Planning permission granted
1 October 2013Appeal allowed
15 July 2016Construction started
28 February 2017Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
28 February 2017
Operator or applicant
Brownieleys Renewables/Muirden Energy
Planning authority
Aberdeenshire
Planning application reference
APP/2012/1121
Turbines
3
Address (REPD)
Nw/O Brownieleys, Fordoun, Alford, Grampian, AB33 1JN
Council area (by location)
Aberdeenshire
Time to decision
77 weeks
Name in REPD
BROWNIELEYS - 3 WIND TURBINES
REPD reference
4348

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Easter Tulloch Wind Farm (Tullo Extension)wind farm25operational1.1
Tullo Wind Farm North Extension (Shiels Wind Farm)wind farm7.5operational1.9
Tullo Wind Farm South (Ext.)wind farm10operational2.1
Hill of Garvock Wind Energy Project (2)wind farm15refused7.3
Hill of Garvock Wind Energy Projectwind farm15application withdrawn7.3
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built7.9
St. Johns Hillwind farm7.7operational8.4
St John Hillwind farm7.7operational8.8
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.8399, -2.3791).