Tullo Wind Farm North Extension (Shiels Wind Farm) (7.5 MW)

Tullo Wind Farm North Extension (Shiels Wind Farm) is a 7.5 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2014; the record was last updated on 20 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
20 March 2014record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
28 July 2011Application submitted
29 February 2012Planning permission granted
30 April 2013Construction started
1 April 2014Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
20 March 2014
Operator or applicant
Eneco
Planning authority
Aberdeenshire
Planning application reference
APP/2011/2389
Turbines
3
Address (REPD)
Laurencekirk
Council area (by location)
Aberdeenshire
Time to decision
31 weeks
REPD reference
3818

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Easter Tulloch Wind Farm (Tullo Extension)wind farm25operational1.2
Tullo Wind Farm South (Ext.)wind farm10operational1.9
Brownieleys - 3 Wind Turbineswind farm7.5operational1.9
Hill of Garvock Wind Energy Projectwind farm15application withdrawn5.7
Hill of Garvock Wind Energy Project (2)wind farm15refused5.7
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built8.5
Boy's Hill Wind Clusterwind farm6.9refused9.2
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built9.4
St. Johns Hillwind farm7.7operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.844, -2.4101).