Boy's Hill Wind Cluster (6.9 MW)

Boy's Hill Wind Cluster is a 6.9 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 October 2013; the record was last updated on 14 February 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
refusedstatus in REPD
14 February 2014record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
10 January 2013Application submitted
21 October 2013Refused by the planning authority

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
refused
Record last updated
14 February 2014
Operator or applicant
Private Developer
Planning authority
Aberdeenshire
Planning application reference
APP/2012/4218
Turbines
3
Address (REPD)
Land to North West of Denside, Glenfarquhar, Auchenblae, Laurencekirk
Council area (by location)
Aberdeenshire
Time to decision
41 weeks
REPD reference
3920

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jacksbank Wind Farm (Glenbervie)wind farm6.8operational5.3
Mid Hill Iwind farm57.5operational5.4
Mid Hill - Phase IIwind farm18.4operational5.4
Forest Avenue Cottage, Drumlithiebattery storage49.9approved, not built7.4
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built7.9
Glendye Estatewind farm104approved, not built8.5
Fetteresso Wind Farm (Mid Hill 3)wind farm42approved, not built8.7
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built9.0
Tullo Wind Farm North Extension (Shiels Wind Farm)wind farm7.5operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9211, -2.467).