Energy Projects Near You

Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storage (9.2 MW)

Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storage is a 9.2 MW solar farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 February 2023, not yet built; the record was last updated on 22 February 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWsolar farm
approved, not builtstatus in REPD
22 February 2023record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
18 August 2022Application submitted
10 February 2023Planning permission granted

Project details

Technology
solar farm
Capacity
9.2 MW
Status (REPD)
approved, not built
Record last updated
22 February 2023
Operator or applicant
East Coast Viners Renewables Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2022/1701
Site area
22.7 ha
Address (REPD)
Adj East Coast Viners Animal Nutrition Drumlithie Stonehaven
Council area (by location)
Aberdeenshire
Time to decision
25 weeks
Name in REPD
Coast Viners Animal Nutrition, Drumlithie - Solar Array & Battery Storage
REPD reference
11976

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Forest Avenue Cottage, Drumlithiebattery storage49.9approved, not built1.2
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built1.8
Meetlaw Farm, Fordounbattery storage49.9approved, not built2.0
West Bendingsbattery storage30approved, not built2.1
Clochnahill Windfarmwind farm6refused2.9
Clochnahill Wind Farmwind farm5.2operational3.2
Old Schoolhouse, Barrasbattery storage49.9application submitted3.6
Brucklaywaird Wind Farmwind farm6.9refused3.8
Jacksbank Wind Farm (Glenbervie)wind farm6.8operational3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9184, -2.3361).