Energy Projects Near You

Meetlaw Farm, Fordoun (49.9 MW battery storage)

Meetlaw Farm, Fordoun is a 49.9 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 September 2023, not yet built; the record was last updated on 4 October 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
4 October 2023record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
4 January 2023Application submitted
19 September 2023Planning permission granted
19 September 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
4 October 2023
Operator or applicant
One Planet Developments Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2022/2676
Address (REPD)
Meetlaw Farm Fordoun Laurencekirk
Council area (by location)
Aberdeenshire
Time to decision
37 weeks
Name in REPD
Meetlaw Farm, Fordoun - Battery Energy Storage System
REPD reference
12361

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Bendingsbattery storage30approved, not built0.5
Clochnahill Windfarmwind farm6refused1.1
Clochnahill Wind Farmwind farm5.2operational1.3
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built2.0
Brucklaywaird Wind Farmwind farm6.9refused2.0
Forest Avenue Cottage, Drumlithiebattery storage49.9approved, not built2.2
Old Schoolhouse, Barrasbattery storage49.9application submitted2.3
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built2.8
St John Hillwind farm7.7operational4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9279, -2.3089).