St John Hill (7.7 MW wind farm)

St John Hill is a 7.7 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 March 2013; the record was last updated on 16 August 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.7 MWwind farm
operationalstatus in REPD
16 August 2013record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
10 July 2008Application submitted
10 December 2009Planning permission granted
7 March 2013Operational

Project details

Technology
wind farm
Capacity
7.7 MW
Status (REPD)
operational
Record last updated
16 August 2013
Operator or applicant
Auquhirie Land Company Ltd
Planning authority
Aberdeenshire
Planning application reference
APP/2008/2570
Turbines
3
Address (REPD)
St John Hill Windfarm Near Roadside of Kinneff, Stonehaven
Council area (by location)
Aberdeenshire
Time to decision
74 weeks
REPD reference
2867

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
St. Johns Hillwind farm7.7operational0.6
Old Schoolhouse, Barrasbattery storage49.9application submitted2.6
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built3.2
West Bendingsbattery storage30approved, not built3.9
Meetlaw Farm, Fordounbattery storage49.9approved, not built4.4
Clochnahill Wind Farmwind farm5.2operational4.6
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built4.8
Clochnahill Windfarmwind farm6refused5.2
Brucklaywaird Wind Farmwind farm6.9refused5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.8935, -2.2724).