Tullo Wind Farm South (Ext.) (10 MW)
Tullo Wind Farm South (Ext.) is a 10 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 July 2014; the record was last updated on 27 November 2014.
10 MWwind farm
operationalstatus in REPD
27 November 2014record last updated
Aberdeenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 28 November 2011 | Application submitted |
| 13 September 2012 | Planning permission granted |
| 1 May 2013 | Construction started |
| 1 July 2014 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- operational
- Record last updated
- 27 November 2014
- Operator or applicant
- Eneco
- Planning authority
- Aberdeenshire
- Planning application reference
- APP/2011/3694
- Turbines
- 4
- Address (REPD)
- Tullo Farm, Laurencekirk AB30 1HS
- Council area (by location)
- Aberdeenshire
- Time to decision
- 41 weeks
- REPD reference
- 4422
Who decides
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Easter Tulloch Wind Farm (Tullo Extension) | wind farm | 25 | operational | 1.1 |
| Tullo Wind Farm North Extension (Shiels Wind Farm) | wind farm | 7.5 | operational | 1.9 |
| Brownieleys - 3 Wind Turbines | wind farm | 7.5 | operational | 2.1 |
| Hill of Garvock Wind Energy Project | wind farm | 15 | application withdrawn | 5.4 |
| Hill of Garvock Wind Energy Project (2) | wind farm | 15 | refused | 5.4 |
| Bridgend Farm, Arbuthnott | battery storage | 49.9 | approved, not built | 9.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.8274, -2.4049).