Hill of Garvock Wind Energy Project (2) (15 MW)

Hill of Garvock Wind Energy Project (2) is a 15 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 October 2004; the record was last updated on 9 May 2006.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refusedstatus in REPD
9 May 2006record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
22 April 2004Application submitted
26 October 2004Refused by the planning authority

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused
Record last updated
9 May 2006
Operator or applicant
Orkney Sustainable Energy
Planning authority
Aberdeenshire
Planning application reference
APP2004/1412
Appeal reference
P/PPA/110/504
Turbines
6
Address (REPD)
East Bradieston Farm Laruencekirk
Council area (by location)
Aberdeenshire
Time to decision
27 weeks
REPD reference
3287

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill of Garvock Wind Energy Projectwind farm15application withdrawn<0.1
Tullo Wind Farm South (Ext.)wind farm10operational5.4
Tullo Wind Farm North Extension (Shiels Wind Farm)wind farm7.5operational5.7
Easter Tulloch Wind Farm (Tullo Extension)wind farm25operational6.2
Brownieleys - 3 Wind Turbineswind farm7.5operational7.3
East Ballochysolar farm39.9approved, not built8.7
Stracathrobattery storage249approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.8205, -2.4931).