Stracathro (249 MW battery storage)

Stracathro is a 249 MW battery storage project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 August 2025, not yet built; the record was last updated on 11 September 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

249 MWbattery storage
approved, not builtstatus in REPD
11 September 2025record last updated
Anguscouncil area

Planning timeline

DateStage
9 January 2025Application submitted
13 August 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
battery storage (stand-alone storage)
Capacity
249 MW
Status (REPD)
approved, not built
Record last updated
11 September 2025
Operator or applicant
Opdenergy UK 8 Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004807
Address (REPD)
Adj Addicate Wood and Huntly Wood & 1.6 km S/O Stracathro Services, Brechin
Council area (by location)
Angus
Time to decision
31 weeks
Name in REPD
Stracathro - Battery Energy Storage System
REPD reference
14042

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
East Ballochysolar farm39.9approved, not built4.8
Arrats Mill, Arratsolar farm18.5approved, not built5.3
Balwyllo Farm, Dun Energy Storage Facilitybattery storage50approved, not built5.7
Dunmill, Substation Dunbattery storage49.9approved, not built5.8
Careston Estatewind farm52application withdrawn9.5
Hill of Garvock Wind Energy Projectwind farm15application withdrawn9.9
Hill of Garvock Wind Energy Project (2)wind farm15refused9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.7615, -2.6141).