Energy Projects Near You

Renewable energy projects in Angus

86 solar, wind or battery projects of 150 kW or more are located in Angus (REPD, July 2026 extract): 5 pending, 42 approved but not running, 8 operational and 17 refused. The council refused 21 of 72 decided applications (29%; UK 19%), with a median 25 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

86projects in the council area
5awaiting a decision
42approved, not running
29%of decisions refused

How Angus decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Projects in Angus

Projects of 1 MW and more (70)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Stracathrobattery storagebattery storage249approved, not builtupdated Sep 2025Jan 2025granted Aug 2025Sep 2025
Tealing Solar Energy Park - Phase 2solar farmsolar farm110approved, not builtupdated Apr 2025Nov 2023granted Mar 2025Apr 2025
Balnuith Farm, Tealingbattery storagebattery storage100approved, not builtupdated Nov 2024Nov 2023granted Oct 2024Nov 2024
Hanna Wind Farmwind farmwind farm81abandonedupdated Sep 2018——Sep 2018
Tealing Battery Energy Storage Farmbattery storagebattery storage80approved, not builtupdated Jan 2024Oct 2021granted Dec 2023Jan 2024
Nathro Hill Wind Farmwind farmwind farm61application withdrawnupdated Nov 2014Jul 2012—Nov 2014
Macritch Hill Wind Farmwind farmwind farm59.4application withdrawnupdated Apr 2016Jan 2015—Apr 2016
Careston Estatewind farmwind farm52application withdrawnupdated Feb 2011——Feb 2011
Balwyllo Farm, Dun Energy Storage Facilitybattery storagebattery storage50approved, not builtupdated Jul 2024Oct 2023granted Mar 2024Jul 2024
Whitehills Energy Storage Facilitybattery storagebattery storage49.9under constructionupdated Mar 2024Jul 2021granted Dec 2021Mar 2024
Templeton Farm, Templetonbattery storagebattery storage49.9approved, not builtupdated Dec 2024Mar 2024granted Nov 2024Dec 2024
Bankhead, Arbirlotbattery storagebattery storage49.9approved, not builtupdated Oct 2024Mar 2024granted Sep 2024Oct 2024
Dunmill, Substation Dunbattery storagebattery storage49.9approved, not builtupdated Nov 2025Jan 2024granted Aug 2024Nov 2025
Carseview Roadbattery storagebattery storage49.9approved, not builtupdated Jul 2025Jan 2025granted Jun 2025Jul 2025
Bonnyknox Solar Farmsolar farmsolar farm49.9application submittedupdated Aug 2025Jul 2025—Aug 2025
Bindwells Battery Storage Facilitybattery storagebattery storage49.9approved, not builtupdated Apr 2026May 2025granted Feb 2026Apr 2026
Solar Farm at Cossans Solar Farmsolar farmsolar farm49.9application submittedupdated Jul 2025May 2025—Jul 2025
Montreathmont Moor Forest Solar Farm & Battery Storagesolar farmsolar farm42approved, not built may be out of dateupdated Apr 2022Jul 2022granted Dec 2022Apr 2022
East Ballochysolar farmsolar farm39.9approved, not built may be out of dateupdated Mar 2020Jan 2020granted Sep 2020Mar 2020
Montreathmont Moorwind farmwind farm38refused on appealupdated Jul 2010Feb 2005refused Jun 2008Jul 2010
Saddle Hill Wind Farmwind farmwind farm35refusedupdated May 2016Nov 2014refused Apr 2016May 2016
Arbroath Battery Storagebattery storagebattery storage35operationalupdated Mar 2026Oct 2018granted Aug 2019Mar 2026
Cossans Solar Farm -ESSbattery storagebattery storage35application submittedupdated Jul 2025May 2025—Jul 2025
Tealing Airfield PVsolar farmsolar farm31permission expiredupdated Apr 2018May 2014granted Dec 2014Apr 2018
Suttieside Farm, Suttieside Road Solar Farm & Battery Storagesolar farmsolar farm31approved, not builtupdated Feb 2025Feb 2023granted Dec 2023Feb 2025
Hillend Of Lownie - Forfar Solar farmsolar farmsolar farm30refusedupdated Jul 2024Jun 2023refused Jun 2024Jul 2024
Pyotdykes Farm, Stoneygroves, Liff Solar Farmsolar farmsolar farm28approved, not builtupdated Oct 2024Oct 2023granted Mar 2024Oct 2024
Wellbank Solar Farmsolar farmsolar farm25approved, not builtupdated Feb 2026Jun 2023granted Feb 2024Feb 2026
Denfield Farmbattery storagebattery storage20approved, not builtupdated Mar 2026Jun 2023granted Jan 2024Mar 2026
Arrats Mill, Arratsolar farmsolar farm18.5approved, not builtupdated Jul 2023Nov 2022granted Jun 2023Jul 2023
Parkhill Farm, Letham Grange Solar Farmsolar farmsolar farm18approved, not builtupdated Sep 2025Apr 2023granted Dec 2023Sep 2025
Corse Hill Wind Farmwind farmwind farm17.5refusedupdated Aug 2012Nov 2011refused Aug 2012Aug 2012
Bamff Wind Farmwind farmwind farm14refused on appealupdated Jun 2014Jun 2012refused Apr 2013Jun 2014
Mile Hillwind farmwind farm13.8application withdrawnupdated Jun 2010Mar 2008refused Oct 2016Jun 2010
Dodd Hillwind farmwind farm12.5refused on appealupdated Jan 2014May 2012refused Mar 2013Jan 2014
Denfield Solar Farmsolar farmsolar farm12.5approved, not builtupdated Mar 2025Oct 2024granted Feb 2025Mar 2025
New Mains Of Guynd Farmsolar farmsolar farm10operationalupdated Mar 2017Jun 2014granted Oct 2014Mar 2017
Orchardbank Industrial Estatebattery storagebattery storage10permission expiredupdated Jul 2020Oct 2017granted Jan 2018Jul 2020
East Ballochybattery storagebattery storage10approved, not built may be out of dateupdated Sep 2020Jan 2020granted Sep 2020Sep 2020
Dragonhall Farm, Padanarambattery storagebattery storage10under constructionupdated Oct 2023May 2021—Oct 2023
Kinnell Farm, Kinnell Solar Farm & Battery Energy Storagesolar farmsolar farm10approved, not builtupdated Dec 2023Jul 2023granted Nov 2023Dec 2023
Frawney Wind Farmwind farmwind farm9.2refusedupdated Dec 2014Jun 2014refused Oct 2014Dec 2014
Ark Hill Wind Farmwind farmwind farm9.2application submitted may be out of dateupdated Oct 2021Oct 2021—Oct 2021
Carrach Wind Farmwind farmwind farm7.2refused on appealupdated Apr 2013Jun 2011refused Aug 2012Apr 2013
Denfieldbattery storagebattery storage7approved, not builtupdated Mar 2025Oct 2024granted Feb 2025Mar 2025
Finavon Wind Farmwind farmwind farm6.9refused on appealupdated Mar 2013Jan 2012refused Oct 2012Mar 2013
Newfordpark House, Glamis Roadrooftop solarrooftop solar6.7approved, not built may be out of dateupdated Feb 2023Nov 2022granted Feb 2023Feb 2023
Craignathro Farmsolar farmsolar farm6.5approved, not builtupdated Apr 2022Feb 2023granted Aug 2023Apr 2022
Ark Hillwind farmwind farm6.4operationalupdated Dec 2014Jul 2003granted Jun 2006Dec 2014
Dusty Drumwind farmwind farm6refusedupdated Dec 2011May 2009refused Dec 2009Dec 2011
Mount Boywind farmwind farm6refused on appealupdated Jan 2010Jan 2007refused May 2009Jan 2010
Craignathro Farmbattery storagebattery storage6approved, not builtupdated Aug 2023Feb 2023granted Aug 2023Aug 2023
Glaxo Smith Kline Wind Turbinewind farmwind farm5refusedupdated Sep 2012Dec 2011refused Aug 2012Sep 2012
Pressock Farmsolar farmsolar farm5operationalupdated Oct 2017Apr 2015granted Oct 2015Oct 2017
Field 279M North East of 15 Tealingsolar farmsolar farm5abandonedupdated Oct 2017Apr 2015granted Nov 2015Oct 2017
West Mains of Kinblethmontsolar farmsolar farm5operationalupdated Apr 2016May 2015granted Sep 2015Apr 2016
Land East of Sandyfordsolar farmsolar farm5permission expiredupdated May 2020Jun 2015granted Sep 2015May 2020
Carsebank Farmsolar farmsolar farm5abandonedupdated Jul 2020Sep 2015granted Dec 2015Jul 2020
Drummygar Solar Parksolar farmsolar farm5abandonedupdated Jun 2018Sep 2015granted Dec 2015Jun 2018
Field 730M West Of Queen Streetsolar farmsolar farm5approved, not built may be out of dateupdated Aug 2020Sep 2015granted Dec 2015Aug 2020
Parkhill Solar Farmsolar farmsolar farm5operationalupdated Apr 2020Nov 2015granted Feb 2016Apr 2020
Dragonhall Farm, Padanaramsolar farmsolar farm5under constructionupdated Oct 2023May 2021granted Sep 2021Oct 2023
Govals Farmwind farmwind farm4.8refusedupdated May 2016Feb 2016refused Mar 2016May 2016
East Skichenwind farmwind farm3.9refusedupdated Sep 2011Jan 2007refused Dec 2009Sep 2011
Witton Farm wind clusterwind farmwind farm3application withdrawnupdated Oct 2013Mar 2013—Oct 2013
Arbikie Wind Clusterwind farmwind farm2.4application withdrawnupdated Jan 2015Dec 2013—Jan 2015
Balnacake Farmwind farmwind farm1.2application withdrawnupdated Apr 2013Aug 2012—Apr 2013
Crofts Farmwind farmwind farm1refusedupdated Jan 2015Jan 2014refused Dec 2014Jan 2015
Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbinewind turbinewind turbine1operationalupdated May 2026Feb 2022—May 2026
Lochhead Farmouse, Lochheadsolar farmsolar farm1approved, not builtupdated Dec 2025Jun 2025granted Sep 2025Dec 2025
Smaller schemes under 1 MW, mostly rooftop solar (16)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Peasiehill Road, Elliot Industrial Estaterooftop solarrooftop solar0.8approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025
North Mains Of Cononsyth Farm, Cononsythwind turbinewind turbine0.8refusedupdated Mar 2026Oct 2025refused Jan 2026Mar 2026
Baker Hughes, Charleton Roadrooftop solarrooftop solar0.7approved, not builtupdated May 2026Mar 2026granted Apr 2026May 2026
Craignathro Farmwind turbinewind turbine0.5application submittedupdated May 2026Mar 2026—May 2026
Leisure Centre, Ethiebeaton Parkrooftop solarrooftop solar0.4approved, not builtupdated Feb 2024Sep 2023granted Feb 2024Feb 2024
Wastewater Treatment Workssolar farmsolar farm0.4approved, not built may be out of dateupdated Apr 2022Apr 2022granted Jul 2022Apr 2022
Lossie Seafoods, Sir William Smith Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025
Sir William Smith Road, Kirkton Industrial Estaterooftop solarrooftop solar0.3approved, not built may be out of dateupdated Jul 2023Apr 2023granted Jun 2023Jul 2023
Stracathro Hospital Solarsolar farmsolar farm0.2operationalupdated Apr 2021Oct 2020granted Apr 2021Apr 2021
Lochhead Steading Concrete Block Manufacturing Plantrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Oct 2019Sep 2019granted Nov 2019Oct 2019
Castleton Of Eassie Solar Photovoltaicsrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Oct 2021Sep 2021granted Oct 2021Oct 2021
Montreathmont Moor Forest Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Oct 2024Jul 2022granted Dec 2022Oct 2024
Suttieside Farm, Suttieside Road Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Feb 2025Feb 2023granted Dec 2023Feb 2025
Kinnell Farm, Kinnell Solar Farm & Battery Energy Storagebattery storagebattery storage—approved, not builtupdated Dec 2023Jul 2023granted Nov 2023Dec 2023
Adjacent Rosehill Resevoir, Ethie Solar Photovoltaic Panel Arraysolar farmsolar farm—approved, not built may be out of dateupdated May 2023Jan 2023granted May 2023May 2023
Hillend Of Lownie - Forfar Solar farmbattery storagebattery storage—refusedupdated Jul 2024Jun 2023refused Jun 2024Jul 2024

Postcode districts in Angus

DistrictProjects within 10 kmPendingApprovedOperational
DD717192
DD8263130
DD915191
DD1011053
DD11231116

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Angus by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.