Drummygar Solar Park (5 MW)

Drummygar Solar Park is a 5 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 22 June 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
22 June 2018record last updated
Anguscouncil area

Planning timeline

DateStage
21 September 2015Application submitted
1 December 2015Planning permission granted
1 December 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
22 June 2018
Operator or applicant
BWE Partnership
Planning authority
Angus
Planning application reference
15/00873/FULL
Site area
10.1 ha
Address (REPD)
Field 275M South of Carmyllie, Arbroath
Council area (by location)
Angus
Time to decision
10 weeks
REPD reference
5646

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Mains Of Guynd Farmsolar farm10operational1.6
Dusty Drumwind farm6refused1.6
Bonnyknox Solar Farmsolar farm49.9application submitted3.5
Bindwells Battery Storage Facilitybattery storage49.9approved, not built4.0
Bankhead, Arbirlotbattery storage49.9approved, not built5.6
Denfield Solar Farmsolar farm12.5approved, not built5.8
Pressock Farmsolar farm5operational5.9
Denfieldbattery storage7approved, not built6.6
Arbroath Battery Storagebattery storage35operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5838, -2.728).