Arbroath Battery Storage (35 MW)

Arbroath Battery Storage is a 35 MW battery storage project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 April 2024; the record was last updated on 6 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWbattery storage
operationalstatus in REPD
6 March 2026record last updated
Anguscouncil area

Planning timeline

DateStage
23 October 2018Application submitted
1 February 2019Refused by the planning authority
26 April 2019Appeal lodged
20 August 2019Planning permission granted
20 August 2019Appeal allowed
2 April 2024Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
35 MW
Status (REPD)
operational
Record last updated
6 March 2026
Operator or applicant
Coronation Power / Persimmon Homes
Planning authority
Angus
Planning application reference
18/00810/FULL
Appeal reference
19/00004/REFUSE
Address (REPD)
Land To East Of Crudie Acre Co, Arbroath, Tayside
Council area (by location)
Angus
Time to decision
43 weeks
REPD reference
7163

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Denfield Farmbattery storage20approved, not built0.1
Denfieldbattery storage7approved, not built0.7
Bankhead, Arbirlotbattery storage49.9approved, not built1.3
Denfield Solar Farmsolar farm12.5approved, not built1.3
Bindwells Battery Storage Facilitybattery storage49.9approved, not built2.9
Parkhill Farm, Letham Grange Solar Farmsolar farm18approved, not built4.3
Corse Hill Wind Farmwind farm17.5refused4.4
Parkhill Solar Farmsolar farm5operational4.8
Bonnyknox Solar Farmsolar farm49.9application submitted5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5651, -2.6205).