Corse Hill Wind Farm (17.5 MW)

Corse Hill Wind Farm is a 17.5 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 7 August 2012; the record was last updated on 29 August 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.5 MWwind farm
refusedstatus in REPD
29 August 2012record last updated
Anguscouncil area

Planning timeline

DateStage
15 November 2011Application submitted
7 August 2012Refused by the planning authority

Project details

Technology
wind farm
Capacity
17.5 MW
Status (REPD)
refused
Record last updated
29 August 2012
Operator or applicant
West Coast Energy
Planning authority
Angus
Planning application reference
11/01093/EIAL
Turbines
7
Address (REPD)
Land At Nether Kelly, Nether Kelly, Arbroath
Council area (by location)
Angus
Time to decision
38 weeks
REPD reference
3875

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bonnyknox Solar Farmsolar farm49.9application submitted4.3
Arbroath Battery Storagebattery storage35operational4.4
Denfield Farmbattery storage20approved, not built4.5
Bankhead, Arbirlotbattery storage49.9approved, not built4.6
Denfieldbattery storage7approved, not built5.0
Denfield Solar Farmsolar farm12.5approved, not built5.0
Bindwells Battery Storage Facilitybattery storage49.9approved, not built5.2
New Mains Of Guynd Farmsolar farm10operational6.2
Dusty Drumwind farm6refused6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.529, -2.6504).