Energy Projects Near You

Bonnyknox Solar Farm (49.9 MW)

Bonnyknox Solar Farm is a 49.9 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 1 July 2025, no decision recorded; the record was last updated on 14 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedstatus in REPD
14 August 2025record last updated
Anguscouncil area

Planning timeline

DateStage
1 July 2025Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
14 August 2025
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Angus
Planning application reference
25/00339/FULM
Site area
95.5 ha
Address (REPD)
Fallaws Of Arbirlot Arbirlot
Council area (by location)
Angus
REPD reference
16666

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Mains Of Guynd Farmsolar farm10operational2.1
Dusty Drumwind farm6refused2.4
Bindwells Battery Storage Facilitybattery storage49.9approved, not built3.1
Drummygar Solar Parksolar farm5abandoned3.5
Bankhead, Arbirlotbattery storage49.9approved, not built4.0
Corse Hill Wind Farmwind farm17.5refused4.3
Denfield Solar Farmsolar farm12.5approved, not built4.4
Arbroath Battery Storagebattery storage35operational5.0
Denfieldbattery storage7approved, not built5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5558, -2.7006).