Bindwells Battery Storage Facility (49.9 MW)

Bindwells Battery Storage Facility is a 49.9 MW battery storage project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 February 2026, not yet built; the record was last updated on 7 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
7 April 2026record last updated
Anguscouncil area

Planning timeline

DateStage
26 May 2025Application submitted
4 February 2026Planning permission granted
4 February 2033Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 April 2026
Operator or applicant
OPDE UK Limted
Planning authority
Angus
Planning application reference
25/00249/FULM
Address (REPD)
Land 150M South Of Annfield Cottage Brax
Council area (by location)
Angus
Time to decision
36 weeks
REPD reference
18013

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bankhead, Arbirlotbattery storage49.9approved, not built1.6
Denfield Solar Farmsolar farm12.5approved, not built1.8
Denfieldbattery storage7approved, not built2.6
New Mains Of Guynd Farmsolar farm10operational2.7
Arbroath Battery Storagebattery storage35operational2.9
Denfield Farmbattery storage20approved, not built3.0
Bonnyknox Solar Farmsolar farm49.9application submitted3.1
Drummygar Solar Parksolar farm5abandoned4.0
Dusty Drumwind farm6refused4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.5751, -2.6646).