Energy Projects Near You

Kinnell Farm, Kinnell Solar Farm & Battery Energy Storage (10 MW)

Kinnell Farm, Kinnell Solar Farm & Battery Energy Storage is a 10 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 November 2023, not yet built; the record was last updated on 13 December 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
13 December 2023record last updated
Anguscouncil area

Planning timeline

DateStage
14 July 2023Application submitted
20 November 2023Planning permission granted
20 November 2032Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
13 December 2023
Operator or applicant
One Planet Developments Limited
Planning authority
Angus
Planning application reference
23/00484/FULL
Site area
37.0 ha
Address (REPD)
Kinnell Farm, Kinnell, Arbroath
Council area (by location)
Angus
Time to decision
18 weeks
Name in REPD
Kinnell Farm, Kinnell - Solar Farm & Battery Energy Storage
REPD reference
12632

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Mains of Kinblethmontsolar farm5operational3.7
Montreathmont Moor Forest Solar Farm & Battery Storagesolar farm42approved, not built4.0
Montreathmont Moorwind farm38refused on appeal4.2
Pressock Farmsolar farm5operational4.5
Parkhill Farm, Letham Grange Solar Farmsolar farm18approved, not built4.5
Parkhill Solar Farmsolar farm5operational5.0
Mount Boywind farm6refused on appeal5.3
Denfield Solar Farmsolar farm12.5approved, not built7.5
Bindwells Battery Storage Facilitybattery storage49.9approved, not built7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.641, -2.6323).