Mount Boy (6 MW wind farm)

Mount Boy is a 6 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 June 2009; the record was last updated on 4 January 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
refused on appealstatus in REPD
4 January 2010record last updated
Anguscouncil area

Planning timeline

DateStage
10 January 2007Application submitted
27 May 2009Refused by the planning authority
26 June 2009Appeal refused

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
refused on appeal
Record last updated
4 January 2010
Operator or applicant
Novera / West Coast Energy
Planning authority
Angus
Planning application reference
07/00050/FUL
Turbines
3
Address (REPD)
Mountboy, Rossie Moor, Angus
Council area (by location)
Angus
Time to decision
124 weeks
REPD reference
2918

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kinnell Farm, Kinnell Solar Farm & Battery Energy Storagesolar farm10approved, not built5.3
West Mains of Kinblethmontsolar farm5operational6.2
Arrats Mill, Arratsolar farm18.5approved, not built6.4
Balwyllo Farm, Dun Energy Storage Facilitybattery storage50approved, not built6.5
Dunmill, Substation Dunbattery storage49.9approved, not built6.5
Parkhill Solar Farmsolar farm5operational6.7
Montreathmont Moorwind farm38refused on appeal7.0
Parkhill Farm, Letham Grange Solar Farmsolar farm18approved, not built7.3
Montreathmont Moor Forest Solar Farm & Battery Storagesolar farm42approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6617, -2.5543).