Mile Hill (13.8 MW wind farm)

Mile Hill is a 13.8 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 9 June 2010; the record was last updated on 9 June 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
application withdrawnstatus in REPD
9 June 2010record last updated
Anguscouncil area

Planning timeline

DateStage
31 March 2008Application submitted
9 June 2010Application withdrawn
19 October 2016Refused by the planning authority

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
application withdrawn
Record last updated
9 June 2010
Operator or applicant
Airtricity Developments
Planning authority
Angus
Planning application reference
08/00426/F
Turbines
6
Address (REPD)
Kingoldrum, Kirriemuir, Tayside, Angus. DD8 5HX
Council area (by location)
Angus
Time to decision
446 weeks
REPD reference
2703

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hanna Wind Farmwind farm81abandoned<0.1
Solar Farm at Cossans Solar Farmsolar farm49.9application submitted5.7
Cossans Solar Farm -ESSbattery storage35application submitted5.7
Land East of Sandyfordsolar farm5permission expired6.2
Dragonhall Farm, Padanaramsolar farm5under construction6.5
Carrach Wind Farmwind farm7.2refused on appeal6.9
Orchardbank Industrial Estatebattery storage10permission expired8.6
Newfordpark House, Glamis Roadrooftop solar6.7approved, not built8.8
Haughend Farm - Alyth Battery Energy Storage Systembattery storage900approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.668, -3.0431).