Energy Projects Near You

Dragonhall Farm, Padanaram (5 MW solar farm)

Dragonhall Farm, Padanaram is a 5 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2022; the record was last updated on 30 October 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
under constructionstatus in REPD
30 October 2023record last updated
Anguscouncil area

Planning timeline

DateStage
12 May 2021Application submitted
22 September 2021Planning permission granted
1 June 2022Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
under construction
Record last updated
30 October 2023
Operator or applicant
Ecosse Solar Parks Limited
Planning authority
Angus
Planning application reference
21/00271/FULL
Site area
8.0 ha
Address (REPD)
Field 275M East Of Dragonhall Farm Padanaram Forfar
Council area (by location)
Angus
Time to decision
19 weeks
Name in REPD
Dragonhall Farm, Padanaram - Solar Photovoltaic Array
REPD reference
9065

The scheme also includes 10 MW of battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Orchardbank Industrial Estatebattery storage10permission expired2.3
Newfordpark House, Glamis Roadrooftop solar6.7approved, not built2.5
Land East of Sandyfordsolar farm5permission expired2.6
Cossans Solar Farm -ESSbattery storage35application submitted3.2
Solar Farm at Cossans Solar Farmsolar farm49.9application submitted3.2
Carseview Roadbattery storage49.9approved, not built3.4
Suttieside Farm, Suttieside Road Solar Farm & Battery Storagesolar farm31approved, not built3.9
Whitehills Energy Storage Facilitybattery storage49.9under construction4.2
Craignathro Farmsolar farm6.5approved, not built4.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6539, -2.9392).