Energy Projects Near You

Suttieside Farm, Suttieside Road Solar Farm & Battery Storage (31 MW)

Suttieside Farm, Suttieside Road Solar Farm & Battery Storage is a 31 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 December 2023, not yet built; the record was last updated on 3 February 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31 MWsolar farm
approved, not builtstatus in REPD
3 February 2025record last updated
Anguscouncil area

Planning timeline

DateStage
20 February 2023Application submitted
13 December 2023Planning permission granted
13 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
31 MW
Status (REPD)
approved, not built
Record last updated
3 February 2025
Operator or applicant
Relay Suttieside Limited
Planning authority
Angus
Planning application reference
22/00870/FULM
Site area
54.4 ha
Address (REPD)
800M N/O Suttieside Farm Suttieside Road Forfar
Council area (by location)
Angus
Time to decision
42 weeks
Name in REPD
Suttieside Farm, Suttieside Road - Solar Farm & Battery Storage
REPD reference
12213

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitehills Energy Storage Facilitybattery storage49.9under construction0.4
Carseview Roadbattery storage49.9approved, not built0.7
Newfordpark House, Glamis Roadrooftop solar6.7approved, not built2.9
Carsebank Farmsolar farm5abandoned3.0
Orchardbank Industrial Estatebattery storage10permission expired3.0
Craignathro Farmsolar farm6.5approved, not built3.1
Finavon Wind Farmwind farm6.9refused on appeal3.9
Dragonhall Farm, Padanaramsolar farm5under construction3.9
Field 730M West Of Queen Streetsolar farm5approved, not built4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6565, -2.875).