Carseview Road (49.9 MW battery storage)

Carseview Road is a 49.9 MW battery storage project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 June 2025, not yet built; the record was last updated on 15 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
15 July 2025record last updated
Anguscouncil area

Planning timeline

DateStage
6 January 2025Application submitted
11 June 2025Planning permission granted
11 June 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
15 July 2025
Operator or applicant
Unknown
Planning authority
Angus
Planning application reference
24/00765/FULM
Address (REPD)
Former Gasworks, Carseview Road, Forfar
Council area (by location)
Angus
Time to decision
22 weeks
Name in REPD
Carseview Road - Battery Energy Storage System
REPD reference
15494

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Suttieside Farm, Suttieside Road Solar Farm & Battery Storagesolar farm31approved, not built0.7
Whitehills Energy Storage Facilitybattery storage49.9under construction0.8
Newfordpark House, Glamis Roadrooftop solar6.7approved, not built2.2
Orchardbank Industrial Estatebattery storage10permission expired2.4
Craignathro Farmsolar farm6.5approved, not built2.7
Dragonhall Farm, Padanaramsolar farm5under construction3.4
Carsebank Farmsolar farm5abandoned3.6
Finavon Wind Farmwind farm6.9refused on appeal4.5
Land East of Sandyfordsolar farm5permission expired4.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6527, -2.8833).