Craignathro Farm (6.5 MW solar farm)

Craignathro Farm is a 6.5 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 August 2023, not yet built; the record was last updated on 7 April 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWsolar farm
approved, not builtstatus in REPD
7 April 2022record last updated
Anguscouncil area

Planning timeline

DateStage
9 February 2023Application submitted
17 August 2023Planning permission granted
17 August 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
6.5 MW
Status (REPD)
approved, not built
Record last updated
7 April 2022
Operator or applicant
Craignathro Farms Limited
Planning authority
Angus
Planning application reference
23/00077/FULL
Site area
8.8 ha
Address (REPD)
Field 430 West Of Craignathro Farm
Council area (by location)
Angus
Time to decision
27 weeks
Name in REPD
Craignathro Farm - Solar Array
REPD reference
10962

The scheme also includes 6 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newfordpark House, Glamis Roadrooftop solar6.7approved, not built2.1
Orchardbank Industrial Estatebattery storage10permission expired2.4
Carseview Roadbattery storage49.9approved, not built2.7
Whitehills Energy Storage Facilitybattery storage49.9under construction2.8
Suttieside Farm, Suttieside Road Solar Farm & Battery Storagesolar farm31approved, not built3.1
Hillend Of Lownie - Forfar Solar farmsolar farm30refused3.2
Dragonhall Farm, Padanaramsolar farm5under construction4.6
Solar Farm at Cossans Solar Farmsolar farm49.9application submitted5.8
Cossans Solar Farm -ESSbattery storage35application submitted5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6289, -2.8796).