Energy Projects Near You

Field 730M West Of Queen Street (5 MW solar farm)

Field 730M West Of Queen Street is a 5 MW solar farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 December 2015, not yet built; the record was last updated on 5 August 2020. REPD also records that the planning permission expired on 4 December 2018, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
5 August 2020record last updated
Anguscouncil area

REPD also records that the planning permission expired on 4 December 2018, so the project may not go ahead in this form.

Planning timeline

DateStage
14 September 2015Application submitted
3 December 2015Planning permission granted
4 December 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
5 August 2020
Operator or applicant
Howmuir Solar
Planning authority
Angus
Planning application reference
15/00864/FULL
Site area
18.0 ha
Address (REPD)
Field 730M West of Queen Street, Carsegownie, Forfar, Tayside
Council area (by location)
Angus
Time to decision
11 weeks
REPD reference
5655

Who decides

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Finavon Wind Farmwind farm6.9refused on appeal0.5
Carsebank Farmsolar farm5abandoned1.4
Suttieside Farm, Suttieside Road Solar Farm & Battery Storagesolar farm31approved, not built4.2
Whitehills Energy Storage Facilitybattery storage49.9under construction4.2
Carseview Roadbattery storage49.9approved, not built4.8
Hillend Of Lownie - Forfar Solar farmsolar farm30refused6.3
Craignathro Farmsolar farm6.5approved, not built6.8
Careston Estatewind farm52application withdrawn6.9
Newfordpark House, Glamis Roadrooftop solar6.7approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6819, -2.825).