Carrach Wind Farm (7.2 MW)
Carrach Wind Farm is a 7.2 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 January 2013; the record was last updated on 19 April 2013.
7.2 MWwind farm
refused on appealstatus in REPD
19 April 2013record last updated
Anguscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 21 June 2011 | Application submitted |
| 30 August 2012 | Refused by the planning authority |
| 10 January 2013 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 7.2 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 19 April 2013
- Operator or applicant
- The Carrach Wind Farm LLP
- Planning authority
- Angus
- Planning application reference
- 11/00554/FULL
- Appeal reference
- 12/00017/REFUSE
- Turbines
- 9
- Address (REPD)
- Land At Welton And Kinclune Hills, Kingoldrum
- Council area (by location)
- Angus
- Time to decision
- 62 weeks
- REPD reference
- 2779
Who decides
| Applications | Angus | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 72 | 10,236 |
| Refused | 21 (29%) | 19% |
| Solar refused | 1 of 36 | 12% |
| Onshore wind refused | 18 of 19 | 45% |
| Battery storage refused | 2 of 17 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Macritch Hill Wind Farm | wind farm | 59.4 | application withdrawn | 5.9 |
| Bamff Wind Farm | wind farm | 14 | refused on appeal | 6.4 |
| Hanna Wind Farm | wind farm | 81 | abandoned | 6.9 |
| Mile Hill | wind farm | 13.8 | application withdrawn | 6.9 |
| Haughend Farm - Alyth Battery Energy Storage System | battery storage | 900 | approved, not built | 9.5 |
| Saddle Hill Wind Farm | wind farm | 35 | refused | 9.6 |
| Drumderg | wind farm | 36.8 | operational | 9.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6956, -3.1448).