Solar, wind and battery projects near Alyth (PH11)
12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH11 (Perth and Kinross): 1 is waiting for a planning decision, 4 approved but not yet running, 3 operational. The largest live scheme is Haughend Farm - Alyth Battery Energy Storage System (900 MW battery storage, approved on 26 November 2024, not yet built), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PH11
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Drumdergwind farm | wind farm | 36.8 | operationalupdated Oct 2013 | Nov 2003 | granted Feb 2005 | Oct 2013 | Perth and Kinross | 1.7 |
| Welton of Creuchieswind farm | wind farm | 9.2 | application withdrawnupdated Oct 2015 | Sep 2015 | — | Oct 2015 | Perth and Kinross | 2.5 |
| West Pitnacree Farm, Alythsolar farm | solar farm | 49.9 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 | Perth and Kinross | 2.6 |
| Welton Of Creuchieswind farm | wind farm | 9.2 | operationalupdated Apr 2018 | May 2010 | granted Jul 2012 | Apr 2018 | Perth and Kinross | 2.8 |
| Bamff Wind Farmwind farm | wind farm | 14 | refused on appealupdated Jun 2014 | Jun 2012 | refused Apr 2013 | Jun 2014 | Angus | 3.6 |
| Tullymurdoch Wind Farmwind farm | wind farm | 14.4 | operationalupdated Apr 2018 | Aug 2012 | granted Sep 2014 | Apr 2018 | Perth and Kinross | 5.2 |
| Haughend Farm - Alyth Battery Energy Storage Systembattery storage | battery storage | 900 | approved, not builtupdated Dec 2024 | Dec 2022 | granted Nov 2024 | Dec 2024 | Perth and Kinross | 5.6 |
| Saddle Hill Wind Farmwind farm | wind farm | 35 | refusedupdated May 2016 | Nov 2014 | refused Apr 2016 | May 2016 | Angus | 6.7 |
| Carrach Wind Farmwind farm | wind farm | 7.2 | refused on appealupdated Apr 2013 | Jun 2011 | refused Aug 2012 | Apr 2013 | Angus | 8.4 |
Smaller schemes under 1 MW, mostly rooftop solar (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| East Gormack Farmsolar farm | solar farm | 0.8 | approved, not built may be out of dateupdated Jun 2023 | Jan 2023 | granted May 2023 | Jun 2023 | Perth and Kinross | 9.7 |
| East Gormack Farmbattery storage | battery storage | — | approved, not built may be out of dateupdated Jun 2023 | Jan 2023 | granted May 2023 | Jun 2023 | Perth and Kinross | 9.7 |
| Castleton Of Eassie Solar Photovoltaicsrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Oct 2021 | Sep 2021 | granted Oct 2021 | Oct 2021 | Angus | 9.7 |
Distance from the average position of the PH11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 1 | 1 | 0 | 0 | 50.6 |
| Rooftop solar | 1 | 0 | 1 | 0 | 0 | 0.2 |
| Wind farm | 7 | 0 | 0 | 3 | 3 | 0 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 900 |
MW in pipeline: pending, approved and under-construction capacity.
How Perth and Kinross decides solar, wind and battery applications
| Applications | Perth and Kinross | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 73 | 10,236 |
| Refused | 32 (44%) | 19% |
| Solar refused | 6 of 24 | 12% |
| Onshore wind refused | 23 of 31 | 45% |
| Battery storage refused | 3 of 18 | 16% |
| Median time from submission to decision | 28.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
All projects in Perth and Kinross
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PH11, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.