Energy Projects Near You

Solar, wind and battery projects near Alyth (PH11)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH11 (Perth and Kinross): 1 is waiting for a planning decision, 4 approved but not yet running, 3 operational. The largest live scheme is Haughend Farm - Alyth Battery Energy Storage System (900 MW battery storage, approved on 26 November 2024, not yet built), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
1awaiting a decision
4approved, not running
3operational

Projects within 10 km of PH11

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Drumdergwind farmwind farm36.8operationalupdated Oct 2013Nov 2003granted Feb 2005Oct 2013Perth and Kinross1.7
Welton of Creuchieswind farmwind farm9.2application withdrawnupdated Oct 2015Sep 2015—Oct 2015Perth and Kinross2.5
West Pitnacree Farm, Alythsolar farmsolar farm49.9application submittedupdated Jun 2025May 2025—Jun 2025Perth and Kinross2.6
Welton Of Creuchieswind farmwind farm9.2operationalupdated Apr 2018May 2010granted Jul 2012Apr 2018Perth and Kinross2.8
Bamff Wind Farmwind farmwind farm14refused on appealupdated Jun 2014Jun 2012refused Apr 2013Jun 2014Angus3.6
Tullymurdoch Wind Farmwind farmwind farm14.4operationalupdated Apr 2018Aug 2012granted Sep 2014Apr 2018Perth and Kinross5.2
Haughend Farm - Alyth Battery Energy Storage Systembattery storagebattery storage900approved, not builtupdated Dec 2024Dec 2022granted Nov 2024Dec 2024Perth and Kinross5.6
Saddle Hill Wind Farmwind farmwind farm35refusedupdated May 2016Nov 2014refused Apr 2016May 2016Angus6.7
Carrach Wind Farmwind farmwind farm7.2refused on appealupdated Apr 2013Jun 2011refused Aug 2012Apr 2013Angus8.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
East Gormack Farmsolar farmsolar farm0.8approved, not built may be out of dateupdated Jun 2023Jan 2023granted May 2023Jun 2023Perth and Kinross9.7
East Gormack Farmbattery storagebattery storage—approved, not built may be out of dateupdated Jun 2023Jan 2023granted May 2023Jun 2023Perth and Kinross9.7
Castleton Of Eassie Solar Photovoltaicsrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Oct 2021Sep 2021granted Oct 2021Oct 2021Angus9.7

Distance from the average position of the PH11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2110050.6
Rooftop solar101000.2
Wind farm700330
Battery storage20200900

MW in pipeline: pending, approved and under-construction capacity.

How Perth and Kinross decides solar, wind and battery applications

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in Perth and Kinross

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PH11, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.