Bamff Wind Farm (14 MW)
Bamff Wind Farm is a 14 MW wind farm project in Angus, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 11 June 2014; the record was last updated on 30 June 2014.
14 MWwind farm
refused on appealstatus in REPD
30 June 2014record last updated
Anguscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 18 June 2012 | Application submitted |
| 26 April 2013 | Refused by the planning authority |
| 11 June 2014 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 14 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 30 June 2014
- Operator or applicant
- Scottish Power Renewables
- Planning authority
- Angus
- Planning application reference
- 12/00963/FLL
- Turbines
- 7
- Address (REPD)
- Bamff Wind Farm, Alyth, Blairgowrie, Tayside, PH11 8DN
- Council area (by location)
- Angus
- Time to decision
- 45 weeks
- REPD reference
- 4098
Who decides
| Applications | Angus | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 72 | 10,236 |
| Refused | 21 (29%) | 19% |
| Solar refused | 1 of 36 | 12% |
| Onshore wind refused | 18 of 19 | 45% |
| Battery storage refused | 2 of 17 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Saddle Hill Wind Farm | wind farm | 35 | refused | 4.2 |
| Welton of Creuchies | wind farm | 9.2 | application withdrawn | 4.3 |
| Welton Of Creuchies | wind farm | 9.2 | operational | 4.5 |
| Tullymurdoch Wind Farm | wind farm | 14.4 | operational | 4.9 |
| Drumderg | wind farm | 36.8 | operational | 5.4 |
| West Pitnacree Farm, Alyth | solar farm | 49.9 | application submitted | 6.1 |
| Carrach Wind Farm | wind farm | 7.2 | refused on appeal | 6.4 |
| Macritch Hill Wind Farm | wind farm | 59.4 | application withdrawn | 6.7 |
| Haughend Farm - Alyth Battery Energy Storage System | battery storage | 900 | approved, not built | 8.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6705, -3.2387).