Energy Projects Near You

West Pitnacree Farm, Alyth (49.9 MW solar farm)

West Pitnacree Farm, Alyth is a 49.9 MW solar farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 20 May 2025, no decision recorded; the record was last updated on 27 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedstatus in REPD
27 June 2025record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
20 May 2025Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
27 June 2025
Operator or applicant
Greentech
Planning authority
Perth and Kinross
Planning application reference
25/00663/FLM
Site area
83.8 ha
Address (REPD)
West Pitnacree Alyth
Council area (by location)
Perth and Kinross
Name in REPD
West Pitnacree Farm, Alyth - Solar Panels
REPD reference
18187

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Drumdergwind farm36.8operational1.2
Welton of Creuchieswind farm9.2application withdrawn3.0
Welton Of Creuchieswind farm9.2operational3.1
Haughend Farm - Alyth Battery Energy Storage Systembattery storage900approved, not built5.5
Tullymurdoch Wind Farmwind farm14.4operational6.0
Bamff Wind Farmwind farm14refused on appeal6.1
Coupar Angus, Pleasance Road Battery Energy Facilitybattery storage49.9approved, not built8.3
Saddle Hill Wind Farmwind farm35refused8.5
Hallyburtonbattery storage100approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.6155, -3.2463).