Welton Of Creuchies (9.2 MW wind farm)

Welton Of Creuchies is a 9.2 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 January 2018; the record was last updated on 3 April 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
operationalstatus in REPD
3 April 2018record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
17 May 2010Application submitted
21 March 2011Refused by the planning authority
29 June 2011Appeal lodged
6 July 2012Planning permission granted
6 July 2012Appeal allowed
19 July 2017Construction started
23 January 2018Operational

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
operational
Record last updated
3 April 2018
Operator or applicant
Green Cat Renewables
Planning authority
Perth and Kinross
Planning application reference
10/00876/FLL
Turbines
4
Address (REPD)
Alyth, Blairgowrie
Council area (by location)
Perth and Kinross
Time to decision
112 weeks
REPD reference
3396

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Welton of Creuchieswind farm9.2application withdrawn0.3
Tullymurdoch Wind Farmwind farm14.4operational2.9
West Pitnacree Farm, Alythsolar farm49.9application submitted3.1
Drumdergwind farm36.8operational3.3
Bamff Wind Farmwind farm14refused on appeal4.5
Saddle Hill Wind Farmwind farm35refused5.5
Green Burn Wind Farmwind farm33abandoned7.9
Haughend Farm - Alyth Battery Energy Storage Systembattery storage900approved, not built8.1