Solar, wind and battery projects near Dundee (DD2)
24 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DD2 (Dundee City): 13 approved but not yet running, 4 operational. The largest live scheme is Tealing Solar Energy Park - Phase 2 (110 MW solar farm, approved on 25 March 2025, not yet built), 9.1 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Levenmouth demonstration turbine (Fife Energy Park) (7 MW, operational), 34.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DD2
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Grange Of Berryhill Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Nov 2025 | Jul 2021 | granted Sep 2022 | Nov 2025 | Dundee City | 0.3 |
| Dundee Technology Parkbattery storage | battery storage | 49.9 | operationalupdated Sep 2020 | Apr 2020 | granted Oct 2020 | Sep 2020 | Dundee City | 1.3 |
| Dunsinane Industrial Estatebattery storage | battery storage | 49.9 | operationalupdated May 2023 | Dec 2019 | granted Feb 2022 | May 2023 | Dundee City | 1.6 |
| Dykes Of Gray Roadsolar farm | solar farm | 2 | approved, not built may be out of dateupdated May 2024 | Sep 2021 | granted Mar 2022 | May 2024 | Perth and Kinross | 2.5 |
| Pyotdykes Farm, Stoneygroves, Liff Solar Farmsolar farm | solar farm | 28 | approved, not builtupdated Oct 2024 | Oct 2023 | granted Mar 2024 | Oct 2024 | Angus | 2.7 |
| The James Hutton Institutesolar farm | solar farm | 2 | approved, not built may be out of dateupdated May 2024 | Oct 2021 | granted Jan 2022 | May 2024 | Perth and Kinross | 2.8 |
| Locarno Works, Brown Streetbattery storage | battery storage | 39.9 | approved, not builtupdated Jul 2024 | Dec 2023 | granted Jun 2024 | Jul 2024 | Dundee City | 3.4 |
| Templeton Farm, Templetonbattery storage | battery storage | 49.9 | approved, not builtupdated Dec 2024 | Mar 2024 | granted Nov 2024 | Dec 2024 | Angus | 3.7 |
| Dormitories Star Inn Farm, Mains Of Fowlisbattery storage | battery storage | 49.9 | approved, not builtupdated Jan 2024 | Aug 2023 | granted Dec 2023 | Jan 2024 | Perth and Kinross | 3.9 |
| New Craigie Retail Parkbattery storage | battery storage | 50 | approved, not builtupdated May 2024 | Feb 2024 | granted May 2024 | May 2024 | Dundee City | 6.1 |
| Pitkerro Roadbattery storage | battery storage | 49.9 | refusedupdated Aug 2025 | Feb 2025 | refused Aug 2025 | Aug 2025 | Dundee City | 6.6 |
| Tealing Airfield PVsolar farm | solar farm | 31 | permission expiredupdated Apr 2018 | May 2014 | granted Dec 2014 | Apr 2018 | Angus | 6.7 |
| Balnuith Farm, Tealingbattery storage | battery storage | 100 | approved, not builtupdated Nov 2024 | Nov 2023 | granted Oct 2024 | Nov 2024 | Angus | 7.2 |
| Wormit Solar Farmsolar farm | solar farm | 4 | operationalupdated Feb 2017 | Jul 2015 | granted Oct 2015 | Feb 2017 | Fife | 7.4 |
| Field 279M North East of 15 Tealingsolar farm | solar farm | 5 | abandonedupdated Oct 2017 | Apr 2015 | granted Nov 2015 | Oct 2017 | Angus | 8.3 |
| Michelin Tyre Co Ltd - Dundeewind farm | wind farm | 4 | operationalupdated Oct 2009 | May 2003 | granted Sep 2004 | Oct 2009 | Dundee City | 8.6 |
| Tealing Solar Energy Park - Phase 2solar farm | solar farm | 110 | approved, not builtupdated Apr 2025 | Nov 2023 | granted Mar 2025 | Apr 2025 | Angus | 9.1 |
| Land To The West Of Kirkton Barns Farmsolar farm | solar farm | 5 | abandonedupdated Sep 2018 | Apr 2015 | granted Oct 2015 | Sep 2018 | Fife | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Harris Academy, Perth Road - Soalr Panelsrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Dundee City | 2.1 |
| Harris Academy, Perth Road - Extension/Roof Solar Photovoltaic Arrayrooftop solar | rooftop solar | — | under constructionupdated Jan 2023 | Jul 2022 | granted Aug 2022 | Jan 2023 | Dundee City | 2.1 |
| Clepington Road Electric Vehicle Charging Hubbattery storage | battery storage | 0.6 | application withdrawnupdated Jan 2022 | Nov 2021 | — | Jan 2022 | Dundee City | 3.0 |
| Police Station, Balunie Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Dundee City | 7.9 |
| Michelin Tyresrooftop solar | rooftop solar | — | abandonedupdated Nov 2018 | Feb 2016 | granted Mar 2016 | Nov 2018 | Dundee City | 8.7 |
| Kirkton Barns Farmwind turbine | wind turbine | 0.2 | application withdrawnupdated Mar 2024 | Sep 2023 | — | Mar 2024 | Fife | 9.7 |
Distance from the average position of the DD2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 0 | 5 | 1 | 0 | 192 |
| Rooftop solar | 4 | 0 | 3 | 0 | 0 | 0.3 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 9 | 0 | 5 | 2 | 1 | 290 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Levenmouth demonstration turbine (Fife Energy Park) | 7 | operationalupdated Nov 2018 | 34.7 |
| Forthwind | 20 | approved, not builtupdated Aug 2023 | 35.1 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Dundee City decides solar, wind and battery applications
| Applications | Dundee City | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 12 | 10,236 |
| Refused | 2 (17%) | 19% |
| Solar refused | 1 of 6 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 24.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DD2, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.