New Craigie Retail Park (50 MW battery storage)

New Craigie Retail Park is a 50 MW battery storage project in Dundee City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 May 2024, not yet built; the record was last updated on 31 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
31 May 2024record last updated
Dundee Citycouncil area

Planning timeline

DateStage
14 February 2024Application submitted
22 May 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
31 May 2024
Operator or applicant
Whirlwind Renewables
Planning authority
Dundee City
Planning application reference
24/00083/FULM
Address (REPD)
1 New Craigie Road, New Craigie Retail Park
Council area (by location)
Dundee City
Time to decision
14 weeks
Name in REPD
New Craigie Retail Park - Battery Energy Storage
REPD reference
16018

Who decides

ApplicationsDundee CityUK
Decided applications (solar, wind, battery)1210,236
Refused2 (17%)19%
Solar refused1 of 612%
Onshore wind refused0 of 145%
Battery storage refused1 of 516%
Median time from submission to decision24.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pitkerro Roadbattery storage49.9refused1.0
Locarno Works, Brown Streetbattery storage39.9approved, not built3.2
Tealing Battery Energy Storage Farmbattery storage80approved, not built4.8
Dunsinane Industrial Estatebattery storage49.9operational4.9
Tealing Airfield PVsolar farm31permission expired5.4
Grange Of Berryhill Solar Farmsolar farm49.9approved, not built5.8
Tealing Solar Energy Park - Phase 2solar farm110approved, not built6.0
Land To The West Of Kirkton Barns Farmsolar farm5abandoned6.1
Balnuith Farm, Tealingbattery storage100approved, not built6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.476, -2.9333).